Signatories to the MOU included the city of Beaumont, town of Devon, city of Edmonton, city of Fort Saskatchewan, city of Leduc, Leduc County, Parkland County, city of Spruce ...
Phase 1 construction was originally anticipated to be complete in 2025 but was completed in December 2023, with the new NAIT/Blatchford Market LRT station opening for passenger...
Edmonton City Council approved and launched the Enhanced Transit Safety Plan in February 2022 to improve safety and accessibility for community members.
The Valley Line Southeast LRT is an integral part of achieving the city of Edmonton’s City Plan and will provide more accessible, convenient and sustainable travel options for...
The funding through The Alberta Transit System Cleanup Grant will support several city initiatives, including the renovation of two vacant cafes into work stations, as well as...
Train testing was briefly paused in June when TransEd identified signaling cables that needed to be replaced along the alignment to improve long-term system reliability.
The 8.1-mile system connects Mill Woods to downtown Edmonton via rail for the first time, stopping at 11 new neighborhood stops, with direct connections to multiple bus lines....
Both city officials and the contractor building the project expressed disappointment in the news and vowed to find a solution to deliver the line into safe operation.
The Community Outreach Transit Team brings together outreach workers from Bent Arrow Traditional Healing Society with Transit Peace Officers from the city of Edmonton to help ...
The Edmonton Transit System (ETS) cash fare is increasing by a nickel as of Feb. 1. Other fare adjustments apply to February fare products, including monthly passes, regardless...
Edmonton Mayor Don Iveson along with Councillors Dave Loken and Bryan Anderson invites Edmontonians and local businesses to help change a life by contributing to the Donate-A-...
Edmonton Mayor Don Iveson and Councillors Dave Loken and Bryan Anderson, as well as representatives from Donate-A-Ride’s corporate donors and the program’s social agency partners...
The city of Edmonton has expanded Wi-Fi service to include the Capital Line LRT. Open City Wi-Fi is available on all 15 platform stations on the Capital Line, bringing the total...
The city of Edmonton has selected TransEd Partners to design, build, operate, maintain and finance stage one of the Valley Line LRT. The 13-km LRT from Mill Woods to Downtown ...