Entering the project development phase allows ATP to become eligible for future reimbursement of allowable costs incurred for the planning and design work to develop the project...
The request to enter project development under the FTA’s CIG New Starts Program comes after the FTA published a Notice of Intent on Jan. 19 to work with the ATP on advancing Austin...
ATP has brought on Brad Cummings as vice president of procurement and contract management and Haley Garcia as senior vice president of program controls in the planning, community...
The recommendation was initially one of five options revealed in March and was selected after planning data analysis, engineering evaluation and community dialogue came together...
The 38th Street to Oltorf to Yellow Jacket option is an on-street, two-line light rail that will cross Lady Bird Lake at Trinity Street and is the most balanced option between...
The options would deliver significantly less light-rail infrastructure than originally planned, but ATP says the revised scope represents a core system that will meet improved...