Metrolinx’s Finch West LRT’s Humber College Station completes structural phase

Feb. 20, 2023
Crews poured 20,000 cubic meters of concrete, installed 650,000 kilograms of steel and completed masonry work to form the skeleton of the Finch West LRT’s western terminus.

Metrolinx’s Finch West LRT’s Humber College Station’s structural phase has been completed. Crews poured 20,000 cubic meters (656,16.8 cubic feet) of concrete, installed 650,000 kilograms (716.5 short tons) of steel and completed masonry work to form the skeleton of the Finch West LRT’s western terminus.

Various teams are now stationed throughout the station box and the north and south entrance buildings, tackling tasks like mechanical, electrical and plumbing installation.

At the north entrance, tarps have been installed to insulate the unfinished building. At the south entrance, crews are busy installing wall tiling in the washrooms and public areas.

The façade of the building is also progressing, with aluminum cladding and the glass curtain wall ready for installation.

Outside the station’s structures, the foundation for the 200-meter (656.2-foot) canopy is now being poured where a walkway will stretch from the station to Humber College campus.