OP-ED: MTA OMNY fare collection ongoing delays

Aug. 25, 2023
Commuters and taxpayers may never know the true final cost for OMNY for several more years after the system is in full use agency wide.

New York Gov. Kathy Hochul and Metropolitan Transportation Authority (MTA) Chairman Janno Lieber's recent celebration of the billionth rider using the One Metro New York (OMNY) fare payment to board the New York City (NYC) Transit subway system was premature. In 2017, the MTA awarded a $573 million contract to Cubic Transportation Systems to replace the Metro Card. New OMNY fare collection technology was originally promised to be coming on line between 2019 and 2023. This date has come and gone. OMNY was designed to speed up passenger boarding. Its primary purpose is to replace the MetroCard, which New Yorkers have used to swipe since 1993 into the MTA NYC subway, bus and Staten Island Railway transit systems.

In 2022, the MTA lost over $600 million to fare evasion. There is no indication in 2023 that this financial loss will be significantly reduced. Neither Gov. Hochul or Lieber is able to explain how the introduction of OMNY in coming years will end routine fare evasion as it continues to flourish today.

Over the past few years, there has been a series of MTA management changes, programming challenges and changing priorities that have all contributed to project implementation delays. Over time, the base contract cost for installation of the new OMNY fare system has grown to $645 million. It has also fallen several years behind the original agreed upon base line schedule between the MTA and contractor. The project is currently $130 million over budget.

Who knows what additional costs may be incurred in coming years. The MTA has never made public any agreed upon detailed recovery schedule from the contractor. This would indicate week by week, month by month and year by year, how the lost time would be made up. It would include resource allocations by the contractor and the MTA to meet the latest recovery schedule.

The MTA is incurring additional costs for its own project management staff and McKissack, its own independent engineering consulting firm providing additional oversight of the contractor for several years beyond what was anticipated. Will the MTA file a claim with the contractor for compensation of these costs?

Costs may continue to grow based upon any change orders due to unforeseen site conditions or last minute changes in technology or scope requested by maintenance or operations groups to the base contracts during ongoing construction.

Long Island Rail Road (LIRR) and Metro-North Rail Road may not reach substantial completion for installation and use of OMNY until late 2025.This will be followed by beneficial use, completion of inspection and acceptance for all work to insure it conforms to contract specifications, punch list items, receipt of asset maintenance plans, followed by release of retainage, and final payment to the contractor(s). Contractors may submit delay claims against the MTA for insufficient facility access, NYC Transit, LIRR or Metro-North Rail Road staff support. Commuters and taxpayers may never know the true final cost for OMNY for several more years after the system is in full use agency wide.

Another critical failure of OMNY that Gov. Hochul, Lieber or their predecessors never acknowledge is the failure to come to any agreement for integration of OMNY with New Jersey Transit, Port Authority Trans Hudson subway and NYC Economic Development Corporation Private Ferry fare collection systems.

The MTA previous plans to phase out the MetroCard in 2023 have been delayed until at least 2025. A majority of riders are still using the Metro Card versus OMNY. While almost 50 percent of subway riders are using OMNY, far fewer are doing the same for those commuters boarding NYC Transit bus, Manhattan Bronx Surface Bus Authority and MTA bus.

MTA's OMNY trials and tribulations will continue for years to come. 

------------------

Larry Penner is a transportation advocate, historian and writer who previously served as a former director for the Federal Transit Administration Region 2 New York Office of Operations and Program Management. This included the development, review, approval and oversight for billions in capital projects and programs for New Jersey Transit, New York Metropolitan Transportation Authority, NYC Transit bus, subway and Staten Island Railway, Long Island and Metro North railroads, MTA Bus, NYCDOT Staten Island Ferry along with 30 other transit agencies in New York and New Jersey.

------------------ 

About the Author

Larry Penner

Larry Penner is a transportation advocate, historian and writer who previously served as a former director for the Federal Transit Administration Region 2 New York Office of Operations and Program Management. This included the development, review, approval and oversight for billions in capital projects and programs for New Jersey Transit, New York Metropolitan Transportation Authority, NYC Transit bus, subway and Staten Island Railway, Long Island and Metro North railroads, MTA Bus, NYCDOT Staten Island Ferry along with 30 other transit agencies in New York and New Jersey.