AB: Edmonton Serves Notice of Default to Metro LRT Signalling Contractor

May 2, 2018
The signalling contractor responsible for Edmonton’s Metro LRT Line has not met the April 30 deadline, city officials said Tuesday.

The signalling contractor responsible for Edmonton’s Metro LRT Line has not met the April 30 deadline, city officials said Tuesday.

The deputy city manager of integrated infrastructure services said they provided Thales with a notice of default under the contract.

Under the contract, Thales will have an opportunity to respond to the notice of default within five business days.

The signalling contract is worth $55 million. The city has already paid $33 million and will withhold the remaining $22 million.

Read the complete article at https://globalnews.ca/news/4179739/edmontons-metro-lrt-line-update-transit/