MTA to perform maintenance, repair and replacement work on Sixth Avenue Line as part of FASTRACK Program

May 5, 2021
The work will require changes to the D and F Subway Line service between Manhattan and Brooklyn for two weekends in May.

Maintenance, cleaning, repair and replacement work will be performed by Metropolitan Transportation Authority (MTA) crews along the Sixth Avenue D and F Subway Lines in Manhattan.

The work will begin May 10 and will last for two weeks through May 21.

While crews from MTA New York City Transit perform track maintenance, repair and cleaning in the corridor, MTA Construction & Development will use the platform and track access created during this time to advance elevator replacement work at 34 St - Herald Sq.

FASTRACK work typically includes:

  • Track – remove debris and repair or replace tie blocks and running rails.
  • Third Rail Operations – clean and remove debris from under and around the third rail.
  • Signals – perform general maintenance on signals and switches.
  • Infrastructure – repair or replace handrails, signs and tunnel lighting. Clean track drains and repair water damage/leaks.
  • Electronic Maintenance – optimize performance of closed-circuit television monitors and cameras. Inspect and test public address system equipment.
  • Station Environment – perform high-intensity station cleaning and painting as well as perform elevator and escalator repair work. Clean vents and drains.

Details about service changes and alternate routes can be found on MTA’s website.