TriMet announces reopening of Steel Bridge following major four-week MAX improvements project

Sept. 2, 2020
MAX and buses returned to regular service over the bridge Aug. 30.

TriMet has concluded the Steel Bridge MAX Improvements Project following 28 days of round-the-clock work, amounting to 672 hours of demolition, construction and testing.

The top deck of the Steel Bridge reopened on Aug. 30, at about 3 a.m. to MAX, bus and auto traffic. This marked the end of TriMet’s biggest light rail revitalization effort in 34 years and represents an important accomplishment in continuing to keep MAX service reliable.

Crews have spent the past four weeks rebuilding the light-rail system across the Steel Bridge from the ground up, chiseling away at concrete, replacing thousands of feet of old rail and installing a new-and-improved signal system, says TriMet. With the new rail and signal equipment in place, the agency says it has strengthened a stretch of light rail, less than half-a-mile long, that’s among the most important and dynamic in the 60-mile system.

Keeping the light-rail system durable

Despite its age, the Steel Bridge typically carries more than 600 MAX trains a day across its upper deck. And, as a critical connection and crossing point for trains on all MAX lines, its health and resiliency has a ripple effect throughout the entire light-rail system.

Installing new and more durable rail, lift joints and locks, as well as replacing switches, switch machines and signal equipment, means fewer issues that could slow or disrupt MAX service. Improvements to the rail and track bed itself will also mean a smoother ride.

Some of the improvements were made for the safety of TriMet employees, including the maintenance-of-way team, who inspect rail and make repairs during normal service hours. The cabinets that house signal equipment were turned to make it easier for the maintenance teams to access them.

On Aug. 29, the project’s final day, TriMet says it ran a train through the area to test every single possible move a train could make. This allowed the team to double check all the new equipment to make sure it is working as intended.

Helping out while spreading out

With no vehicles able to go over the Steel Bridge during the project, shuttle buses moved riders across the Willamette River, using the Broadway and Burnside bridges.

Nearly 200 support staff, mainly TriMet volunteer ride guides, were at MAX stations and shuttle bus stops to assist riders throughout the four-week disruption. TriMet staff dedicated more than 3,800 hours, answering questions, helping riders make connections and promoting physical distancing. They were deployed with face masks and hand sanitizer for those who needed them and informed riders of TriMet’s precautions due to the COVID-19 pandemic. With the pandemic posing a new challenge to an improvement project such as this, concrete decals and signs were placed at transfer points reminding customers to spread out for safety. 

Making transit better

Performing necessary improvements to MAX tracks, switches and equipment helps to improve service by making the system more resilient and minimizing delays and disruptions in the future. Over the past five years, on-time performance of MAX trains has improved from 75 percent in November 2015 to around 90 percent today.

MAX customers will continue to see more improvements in the coming years as TriMet works to rejuvenate the light-rail system to keep trains moving and on schedule. This fall, crews will be back at it, making improvements to the end of the MAX Blue Line in Gresham. This will fully complete the second phase of the Gresham MAX Improvements project, which was started last year.