Specialty infrastructure makes track installation on I-90 floating bridge possible

July 24, 2019
The track bridges and track attachments accommodate lake motion and will allow Sound Transit light-rail trains to traverse the bridge when the Blue Line opens in 2023.

There is nothing straight forward about constructing light-rail infrastructure on top of a floating bridge. Rails must be able to accommodate lake motion - all six ranges of it; stray current risk must be eliminated; weight associated with standard track must be minimized and there is no precedent for such a method. Until now.  

Sound Transit construction crews have been installing rail on the bridge for close to a year. Innovative track bridges accommodate lake motion and will enable light-rail vehicles to transition onto the floating bridge. Additionally, once on the bridge, the light-rail vehicles will operate over rails adhering to the bridge deck with specialized track attachments that minimize weight and isolate stray current from the electric system that powers the trains.

The specialty infrastructure required several years of planning and prep work, including building full-size track bridge prototypes that were tested at the Transportation Technology Center in Pueblo, Colo., and post-tensioning the bridge pontoons to reinforce the concrete with high-strength tensioned strands. Sound Transit explains that post-tensioning enables the bridge to withstand stronger winds and higher waves, as well as strengthen it to carry light-rail tracks and vehicles.

Tracks on the floating bridge are attached to light-weight concrete blocks, which sit on a layer of special shock-absorbing material called corkelast. A special polymer holds it all in place on the bridge deck without having to drill holes into the deck. Nearly 9,000 of these blocks, which also isolate stray current, are being affixed to the bridge deck using a DexG epoxy. Rail is set on the blocks with steel tie bars placed between them to maintain gauge.

Sound Transit says crews have installed one of the track bridges, which were engineered to compensate for the lake’s six ranges of motion and will allow light-rail trains to travel from the fixed sections of the bridge to the floating section. All eight of the track bridges are scheduled to be in place by the end of this year.

When the Blue Line opens in 2023, riders will be able to travel from Mercer Island to the University of Washington in 20 minutes; from South Bellevue to Sea-Tac Airport in 50 minutes; and from Redmond Technology to Bellevue Downtown in 10 minutes. It will also mark the first time light-rail trains operate over a floating bridge.

About the Author

Mischa Wanek-Libman | Editor in Chief

Mischa Wanek-Libman serves as editor in chief of Mass Transit magazine. She is responsible for developing and maintaining the magazine’s editorial direction and is based in the western suburbs of Chicago.

Wanek-Libman has spent more than 20 years covering transportation issues including construction projects and engineering challenges for various commuter railroads and transit agencies. She has been recognized for editorial excellence through her individual work, as well as for collaborative content. 

She is an active member of the American Public Transportation Association's Marketing and Communications Committee and serves as a Board Observer on the National Railroad Construction and Maintenance Association (NRC) Board of Directors.  

She is a graduate of Drake University, where she earned a Bachelor of Arts degree in Journalism and Mass Communication with a major in magazine journalism and a minor in business management.